Many of the lots in the City of Oak Hill sit in districts whose minimum lot sizes are well under an acre.
On November 25, 2025, the Oak Hill Board of Commissioners adopted Ordinance 2025-07, which rewrote parts of the city's zoning, stormwater, fencing and permitting rules.
The Split Rule and District Minimums
The new language in Section 14-121(a)(1) says no existing lot "may be subdivided, or combined with another lot or lots and subdivided unless each of the resulting lots are two (2) acres or more," and that this "does not obviate the necessity of complying with existing lot size regulations." The city's public notice for the October 28, 2025 hearing described it more bluntly as a "Prohibition of subdivision that results in lots smaller than 2 acres."
The district minimums are still there. Under the revised Table II, Zone A requires 10,000 square feet, Zone B 20,000 square feet, Zone C one acre, Zone D two acres, Zone E three acres and Zone F four acres.
The Zone Letter and Table II
Ordinance 2025-06, the companion measure heard the same night, added the revised lot, bulk and density table to the official zoning map without changing the map's district boundaries. The figures below come from that table, with the impervious-coverage limit shown for lots larger than the district minimum, where the "whichever is lesser" test applies.
| Zone | Minimum lot | Minimum front setback | Impervious cap, lots above minimum | Floor-area ratio cap |
|---|---|---|---|---|
| A | 10,000 SF | 60 ft | 40% or 6,000 SF, lesser | See Table II |
| B | 20,000 SF | 60 ft | 36% or 9,000 SF, lesser | See Table II |
| C | 1 acre | 75 ft | 30% or 18,000 SF, lesser | 18%, max 10,000 SF |
| D | 2 acres | 75 ft | 25% or 25,000 SF, lesser | 18%, max 18,000 SF |
| E | 3 acres | 100 ft | 20% or 35,000 SF, lesser | 14%, max 18,000 SF |
| F | 4 acres | 150 ft | 20% or 37,000 SF, lesser | 14%, max 18,000 SF |
The floor-area ratio is gross floor area divided by lot area.
The table's front setback is a fallback figure. Section 14-121(f) sets the front setback as the average of the four nearest lots "with like-facing homes thereon," and uses the table minimum only when that average cannot be determined.
Permits, Tree Protection and Steep-Slope Review
Ordinance 2025-07 and the city's tree standards address permits, tree protection and steep slopes.
- Demolition permit. A city demolition permit is required before a structure comes down. If no replacement plan is submitted, the site must be graded and seeded unless new construction begins within 30 days, and the demolition itself must be finished within 30 days.
- Land-disturbance permit. Disturbing 500 square feet or more triggers this permit, and activity on a parcel is added together over a rolling three-year period. Excavation or fill above 50 cubic yards and work that alters a natural drainage channel are also covered. The permit has to be approved before the city issues a building permit, and the review includes stormwater requirements.
- Tree protection. Oak Hill's tree protection standards require an inventory of trees at least three inches in diameter at breast height before construction, demolition or clearing. Protected trees outside the building envelope generally cannot be removed. Canopy-retention targets run on a sliding scale from 48 to 75 percent of existing canopy, replacement planting must equal 100 percent of the diameter removed, and replacement trees must be maintained for at least three years. The city's Codes Department says erosion control and tree protection must be in place and inspected before construction starts.
- Steep-slope review. Under Section 14-138, any construction on or directly affecting a slope of 15 percent or more that covers at least 1,000 square feet goes to the Planning Commission.
What a Hillside Rebuild Looks Like on Paper
The city's file on Planning Commission case PC 25-13, on Balmoral Drive, shows a hillside rebuild proposal. The application asked to demolish an existing house and driveway and build a new house, driveway, accessory structures and a detention pond on a steep slope. According to the applicant's letter in the city's case packet, the Board of Zoning Appeals granted a 6.3-foot rear-setback encroachment and tree-removal relief on November 18, 2025.
Kimley-Horn's engineering review for the city, dated November 24, 2025, put numbers on it. The plan disturbed 55,616 square feet, most of it on existing slopes of 15 to 20 percent, and added a net 4,966 square feet of impervious surface. It describes a 9,080-square-foot primary house by the floor-area calculation, a 417-square-foot pool cabana, and 11 trees proposed for removal, seven of which needed BZA relief. Stormwater treatment paired a water-quality unit with a dry detention pond, alongside a new series of retaining walls.
A second filing, PC 26-08 on Overton Lea Road in Zone F, appeared on the May 5, 2026 Planning Commission agenda for a new house, pool and pool house on a steep-slope lot. Its engineering review lists 80,586 square feet of disturbed area, about 1.85 acres, with 10,248 square feet of net added impervious surface, permeable pavement and an infiltration trench.
Kitchen and Fence Provisions
Two newer provisions reach inside the design itself. The 2025 rewrite revised the permitted-uses section to state "no more than one kitchen in a single-family dwelling."
Fencing changed again this year. Ordinance 2026-05, adopted August 19, 2026, bars fences in the front yard of any lot in Districts A, B and C. Front-yard fences are allowed in D, E and F up to four feet. The posted text caps rear-yard fences in D, E and F at five feet. Solid fences are limited to the setbacks that apply to accessory structures, and all other fences can be no more than 50 percent opaque.
Quick Answer
Where do I confirm a lot's zone? The City of Oak Hill offices are at 5548 Franklin Pike, Suite 101, and the codified zoning text is on Municode.
This post is general information about published city rules, not legal, engineering or financial advice. Confirm your own lot's zoning and requirements with the City of Oak Hill and the appropriate professionals before you commit to a purchase.
Seven years in residential construction taught me to price the site work first. Anna Rose Marangelli is here when you are ready to Schedule a Consultation.